The project has continued and is beating our expectations. The team contributed very well and we believe that the project has far exceeded our expectations. The Finance department have also come back with a batch improvement valuation. The savings per batch is now calculated at $2056 per batch. There is a cost included here for testing which they were not including at the start of the project but when it was reviewed showed that it was a realistic and large saving to the laboratory department.
Since the 2 failures we have not proceeded with the timing process unless the particle size analysis after application has been complete. The particle size analysis has so far indicated that our D90 should be below 1450 for the processing at 115 TC. As can be seen from the run chart below the results have been in a tight range.
Run chart
We have manufactured 42 batches since the failure and we have noticed considerable improvement on the CP/CPK. Before the project started the CPK was a negative number and now it is positive (CPK 1.61). This can be seen from the chart below.
Process capability chart
If we include the 2 failed batches the CP/CPK is as follows 1.18/1.17 and while both are positive values they are both below the 1.33 minimum expectations.
Process capability chart 2
Our target was to make reductions to the lead time, number of days timing and the cost per timing at the timing stage. The table below shows the current state. Each metric has exceeded our expectations.
Lead time: This has now been adjusted on SAP to reflect 30 days. However with machine and personnel availability the process can be complete in 8 days
Number of days timing: None of the last 42 batches manufactured required day 2 timing so this is exceeding expectations as we had hoped to be 1.5 days timing or less. On SAP we have removed all phases after day 2 timing and we will monitor and review this in 6 months’ time with a view to only leaving 1 timing phase for day 1 only.
Cost per batch at the timing stage: This cost has reduced from a massive $2893 to $847. We had been expecting a smaller figure as we were not getting credit for a considerable reduction in testing which can and actually does add a large cost to each day of timing. Our Finance department reviewed the potential savings and have agreed that there was a large work reduction for the laboratory and have now removed that from the cost of manufacture of each batch. The order for the full year 2013 was expected to be 100 batches but since the start of the project the order has increased to just over 200 batches.
Table with previous and current state
Metric
|
Previous state
|
Current State
|
Lead time
Number of days timing
Cost per batch at the timing stage
|
42 days
2.2 days
$2893 per batch
|
30 days
1 day (last 42 batches)
$837
|
We have made a huge improvement in the stages of processing of this product. We have not changed the formulation of the product but with the help of the DMAIC process we were able to show that the product can be manufactured more efficiently and have a better use of equipment and personnel resources. We will now proceed with an OEE on the equipment as we have shown that the product can be manufactured in 8 days but we will need to show that the equipment effectiveness is in place before we reduce the lead time further. A lead time of 8 days on this product would mean that a customer could have their product 2 months after they have ordered it.
We will present this project to the site leadership team and already I have been asked to apply these learning’s to other products.
Tasks completed
· Changed from 75 timing coats on day 1 to 115 timing coats
· Updated MBR with instruction to remove and test a 10 gram sample for particle size
· Test the sample using the EYECON which is now qualified
· SOP implemented to cover use and cleaning of the EYECON
· Updated the SOP for the process guidelines of the product